Issues in the construction of first bullet train in India?

Question
in progress 0
Hena Gupta 7 months 1 Answer 72 views Intermediate 0

Answer ( 1 )

  1. The first Bullet train is decided to be launched between Mumbai-Ahmedabad for which the Land acquisition is been held in these areas. The issue there is the land acquisition in agricultural area for which the farmers are protesting and the government limiting the compensation fund also increases the tension in the area.

    Japan International Cooperation Agency(JICA) funds this project and thus they in field negotiating with the farmers. JICA promised that their concerns will be addressed with the officials. JICA has the policy of providing the Win-Win compensation funds for those whose lands are acquired.