    Link tasks to a Project 2019,

    1)  Click View > Gantt Chart

    2) Hold down Ctrl and click the two tasks you want to link (in the Task Name column).

    3) Click Task > Link Tasks. Note: 
    Note: To remove a link, select the two linked tasks and then click Task > Unlink Tasks Unlink Tasks button on the Tasks tab of the ribbon. .
    *Insert a task between linked tasks*

    1) Click File > Options.

    2) In the Project Options dialog box, click Schedule and scroll to the Scheduling options in this projectsection.

    3) Select the Autolink inserted or moved tasks check box.

    4) Insert the new task.

    *Link tasks in a Network Diagram*

    1) Click View > Network Diagram

    2) Point to the center of the predecessor task box.

    3) Drag the line to the successor task box.

    *Link tasks in a Calendar*

    1) Click View > Calendar

    2) Point to the predecessor task’s calendar bar.

    3) Drag the line to the successor task’s calendar bar.

    *Link manually scheduled tasks*

    1) Click File > Options.

    2) In the Project Options dialog box, click Schedule and scroll to the Scheduling options in this projectsection.

    3) Uncheck the Update manually scheduled tasks when editing links check box.

    Source: https://support.office.com/en-us/article/link-tasks-in-a-project-31b918ce-4b71-475c-9d6b-0ee501b4be57